I have a problem with the way the program displays and calculates production times per unit.
For example, I have a 500m Factory in france I want to produce Gas in. The stated production time is 0:0:1 h (I am at businessman level). I wish to produce as much as In 24 hours as I can because I tend to log in at about the same time each day. So I do the calculation:
24*60*60 = 86400 * production time of 1 = 86400 Units
I put this on to produce. However the production time comes out at 41+ hours.
The production time per unit is actually approx 1.73s per unit. I have no way of knowing this unless I recorded it from an earlier use or perhaps went onto kapitools (which I can't read and would rather not have to visit every time I want to put on a production run).
So I would like to see production times per unit stated more accurately going down into fractions of seconds (similar to power and water prodution).
Also It would be useful to have a confirmation screen between pressing the 'produce now' button and the production actually starting which states the materials, cost and production time. Similar to what happens now but with a 'confirm' and 'cancel' option rather than the current 'back' option with no choice as to if the production happens or not.
Thanks
Production Times Problem
Moderator: moderators